Rate management is one of TimeControl’s most popular capabilities. Each hour worked on the timesheet can be calculated against a rate value according to the rate table. The end user selects a rate code on the timesheet and as the timesheet is posted, TimeControl calculates the costs.
Each rate code has two values, which are most commonly use for the internal or direct cost of the employee and the external or billable cost. TimeControl supports an unlimited number of codes which allows for many combinations. One of the most common requests is to track project specific costs.
Because there are an unlimited number of charge codes possible for each employee, the amount calculated for each hour of work can be different for each project and for each employee. For a client with a lot of projects, the number of possible rate codes that could be chosen by an employee, could become quite extensive. TimeControl provides a function that minimises the effort required to choose the correct rate code and that increases the accuracy of the entry. This function allows a project- specific rate code to appear when the project is chosen. This rate code will take precedence over any employee defaults that have been specified in the Employee table. To use this configuration, first add the project-specific rate code to the Labour Rate Table as a Global ate code type. This is a requirement for using the project-specific rate function. If you desire an employee-specific project costs, then add a rate with the same rate code value but as an employee specific rate. TimeControl will always select the most specific rate code applicable with that rate code value. So, for example, if the rate table has a rate code called “Std” for Standard rate and that is a Global Rate of $50 and a rate code called “Std” which is an employee specific rate for John, then when John does his timesheet, TimeControl will assume that the “Std” for John is the correct code.
Once the Global rate has been created, then go to the Project Table, and locate the project for which you’d like this rate code to be specified. On the Project Details tab select the project specific rate code.
Note that only global rates can be selected.
Selecting the “required” button will ensure that only this rate can be selected on a timesheet when this project is selected.
When the project is added as a line item to an employee’s timesheet the project specific default rate code will be automatically selected. If a matching employee rate type has been created, the employee rate value will be calculated. The project rate code will take precedence over the default rate code specified in the Employee Table.
In this example, the P_SPEC rate was added automatically to the DA Project line item.