TimeControl includes a number of links to project management tools and a number of different methods of connecting to them.
If using Microsoft Project Standard or Professional, the link is to a desktop tool and that’s always going to be on-demand but what about if you’re linking to Microsoft Project Server, Primavera or Deltek’s Open Plan? Now the link is typically server-to-server and could be scheduled or on-demand. With Project Server, incoming links can also be triggered by the TimeControl “OnPublish” event that is included with the system. Primavera can also be set up to automatically link data to TimeControl when a new project is created. Here’s the best practice that’s most commonly applied:
First for incoming changes in data, this is a link that is meant to keep the TimeControl charge and activity code information up to date with the changes that may exist in the project files. It’s most typical to create the incoming links as scheduled or automatic events. If the link is with Project Server, then the “OnPublish” event module that is part of the installation is perfect for this. If the link is with Open Plan or Primavera then a regular scheduled link moving information on a server-to-server basis is ideal.
How often should the links happen? As often as the project is likely to be updated. For most projects a weekly link will probably be fine. If your week-ending day is Friday, then a link on Thursday night might be appropriate. Some projects are highly dynamic and need to be updated multiple times per week or even multiple times per day. Create as many scheduled events to do this. A scheduled link can be daily or weekly and you can pick the day and/or time when you’d want it to occur.
For project updates that will move timesheet information back to the project management tool, we recommend making most of these links “on-demand” for the project manager. That means that the project manager will pull the data from TimeControl to their project management tool when they are ready for it. You can make the link automatically scheduled of course but we had an image of a project manager working on his project late one night and suddenly “poof” everything changes as the automatic link moves the data in from TimeControl. Most project managers will want to bring in the data when they’re ready to see the project advance.
There may be exceptions of course. Some projects such as regular maintenance projects aren’t really managed the same way and an automatic link to update those files from TimeControl may make more sense. You have the option to do both.
With TimeControl, you get the ability to make your links as automatic or as manual as you wish and each situation can be different.